HMDA Fees and Charges for Building and Layout Applications

HMDA Fees and Charges for Building and Layout Applications

A)    Development Charges (under Section 27 & 28 of the AP Urban Areas (Development) Act, 1975 – Rates as given in G.O.Ms No. 51, MA, Dated: 5-2-1996.

B)    Processing Charges: Building Applications @ Rs. 5/- per sq. mt of proposed built up area; Layout applications and Sub-Division applications @ Rs 2/- per sq. mt of land

C)     Stationery & Publication Charges: Rs. 5000/- per application

D)    In case of plots/sites in unapproved layouts or not forming part of any layout – 10% proportionate open space charges and layout charges.

E)    HUDA Board charges (applicable in Appeal/ NOC Cases)


At the time of application only 10% of Processing Charges are collected. HUDA intimates the rest of the charges and fees after the technical approval.

 TIME-LIMIT FOR DISPOSAL OF APPLICATIONS IN HUDA:


1.         Building Applications:                              30 days

            Scrutiny and approval & intimation of balance fees & Charges:  20 days

            Payment of Fees & Charges & release of Plan to local body:     10  days

                                                                                    Total :                          30  days        

2.         Layout Application:                       60 days

            Scrutiny and approval & intimation of balance fees & Charges: 30 days

            Payment of Fees & Charges & release of Plan to local body:    10  days

            Completion of layout demarcation, fencing of mortgaged area,etc:  10 days

Release of layout after compliance of mortgage deed, submission of Non Encumbrance Certificate:10 days

                                                                        Total :    60 Days

Final Layout Release:

Scrutiny of application & approval for Final Layout:                      10  days

Handing over of open spaces & roads to local body & submission of their Report: 15 days

Release of Final Layout to local Body &  Relinquishment  deed:10 days

3.         NOC Cases:                         

(A)              Normal permissible cases: 30 days

Scrutiny and approval & intimation of balance fees & Charges:20 days

Payment of Fees & Charges & release of Plan to local body:    10  days

                                                                                    Total :                          30  days        

B)    Under Appeal Clause by HUDA Board: After approval by HUDA Board:

intimation of fees & Charges:                                              10 days

Payment of Fees & Charges & release of NOC :             10  days

4.   Land Use Certificates          2 days in respect of Non-MCH Area

                                                         3 days in respect of MCH Area